曹妃甸煤码头起步工程装卸系统设备工程

2016-2-28 01:00:00
2010-06-09
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

工程规模及结构形式:曹妃甸煤码头起步工程建设10万吨级泊位2个、7万吨级泊位1个、5万吨级泊位1个、7万吨级待泊泊位1个,年通过能力为5000万吨。系统设备部分:系统工艺布置分为翻堆线系统及取装线系统,其中:翻堆线系统设备配置为O型转子三大梁结构27次/h的四翻翻车机2台、7780t/h悬臂式堆料机5台及17条皮带机等;取装线系统设备配置为6000t/h悬臂斗轮取料机8台、6000t/h装船机4台及12条皮带机等,并配套建设供电照明、控制及计算机管理、通信、给排水、消防系统以及环境保护设施等。工程部分结构形式:道路堆场为高强砼联锁块铺面结构,地基采用强夯处理,堆料机、取料机轨道基础为现浇钢筋砼轨道梁结构;翻车机房及廊道主体地下构筑物采用现浇钢筋砼结构,围护结构采用现浇钢筋砼连续墙。