CCCC-FHEC Fulfilled Five 12 Targets of Phase III of Shenhua Huanghua Port and Witnessed Ceremony of Full Load Commissioning
CCCC-FHEC Fulfilled Five 12 Targets of Phase III of Shenhua Huanghua Port and Witnessed Ceremony of Full Load Commissioning
A ceremony of full load commissioning of the works for Phase III of Shenhua Huanghua Port was held on 12 December 2012 to declare the complete fulfillment of the five 12 targets of Phase III of Shenhua Huanghua Port.
Attending the ceremony were Xue Jilian, Deputy General Manager of Shenhua Group, Hui Xueyong, member of Standing Committee of CPC Municipal Committee of Cangzhou, Secretary of CPC Working Committee of Bohai New District, Director of Administrative Board of Bohai New District and Secretary of CPC Municipal Committee of Huanghua, Xie Youquan, Board Chairman of Shenhua Huanghua Harbor Admin. Corp., Ltd., Mao Yuanping, General Manager of CCCC-FHEC, and Wu Like and Guo Qiyun, Deputy General Managers of CCCC-FHEC.
The works for Phase III of Huanghua Port was officially commenced on 20 April, 2011 and was commissioned with full loads on 12 December, 2012, 14 days ahead of the schedule, fulfilling successfully the five 12 significant milestones of the project and symbolizing the complete realization of the targets set by Shenhua Group, as a result, Shenhua Huanghua Harbor Admin. Corp., Ltd. will now increase its coal handling capacity by 50 million ton.
Mao Yuanping, General Manager of CCCC-FHEC, Xie Youquan, Board Chairman of Shenhua Huanghua Harbor Admin. Corp., Ltd., and Xue Jilian, Deputy General Manager of Shenhua Group, spoke at the ceremony and Zhu Guochun, General Manager of Project Management for Phase III of Shenhua Huanghua Port, made a presentation on the project.()