港珠澳大桥首节沉管完成历史性海底对接

2017-2-28
2013-05-07
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

2013年5月6日10时10分,港珠澳大桥岛隧工程西人工岛岛头结合部,汽笛悠扬,笑语连连。首节沉管隧道浮运安装完成历史性时刻:E1管节顺利与西人工岛暗埋段实现对接,完成首次“海底之吻”壮举。经过验收,符合设计要求。
    E1管节正式沉放对接是在5月5日夜间进行的,现场施工人员连续作战96小时,顶住高强度作业压力,振奋百倍精神,朝着最终目标发起冲刺。在管节顺利沉放着床后,拉合作业紧接着开展,作业人员首先进行千斤顶搭接,并进行拉合,在对接面形成水力压接条件后,开启阀门排出结合腔内海水和空气,海水巨大的压力推动沉管前压,经过潜水员多番水下检查确认,向管内压载水箱注水,保持沉管一定的抗浮安全系数。
    随着现场测量人员将复核数据传至指挥室,安装组开始拉合距离确认倒计时:5公分、4公分……1公分、5毫米、4毫米……1毫米,初步拉合结束!此时,GINA止水带接触西人工岛暗埋段钢端壳,首节沉管与西人工岛实现“初吻”。
    拉合完成后,现场施工加快对接步伐,水力压接和管内精调紧张展开,在对接高程达到控制范围后,潜水人员进行水下实际探摸,现场检测结果显示,对接端水平偏差和竖向偏差均严格控制在设计范围之内,管节纵坡符合2.996%的高精度坡度要求。
    从5月2日11时E1管节正式出坞开始,至5月6日10时管节对接完成,港珠澳大桥岛隧工程首节沉管浮运安装经历了连续4个昼夜艰难而有意义的“海上之旅”,在项目总经理部的全程指导和公司全体参建人员的砥砺协作下,终于完成首节沉管圆满对接的历史性任务,迈出了沉管隧道安装施工的第一步。