公司承建的黄骅港三期工程正式交付使用

2017-2-28
2013-04-19
01PTtFbnjC+yv5JXPrtzyXP+T9SnWG/ErufYphJQy9e2yNnUYoSzau1mNEd1tJC7C6JUqrVchGxeGE4ZM0PNsyKtcjf53Dt8Rpva6fK8Hm3qejTmomvNJ8KvHOeU/VMxIx2Gle3huJPpRF0upeYUKBERa8kS2I4sSnXwhJKP45Ue+5RVEg5bN1Oz6j4VZ4iYjqmbKpRdk8+cqLCqTujvJZQxfgEXgboREbmdKANZHpwn4oY2X8Kh27wMGbBDo3nl2uZI9xb8as3+22ZM1ymJT7aDdA18xacmMTwsVS1YXuUsL/Jm/tO0WJsMu8mFi8dpJ9MdqoIITQoLQqv5rQwNWIbltZk7ePfCV+pIcbniDbtYw/dEtw8W/kggSwaB6bC3KrhoSqP/b1EYcq4dSVrdx7T874axeVdKmo7KiHKRmIE2FB6cxUgjIVPdfTTmsbPzv9m4tDqLaJcdBAjeatfwSVym05MDcNS/VInYVkqCzo3ZZWU1NOJOr0STSyoN1Nym+of4Vexe4d22yNnUYoSzau1mNEd1tJC7j0Yh6V9LHY7XLnblpRiqXJaIpTrOoMXkWMlG+M8jN+PseLp+9qQ1RctmMp2wTrCFP1WeRlz2lYrarAZwNuk8LtmtEuPMpWyiLm9spQEQ512svtdehocNK1NlMRx7BdxaUcshpgA9siO7n7/DLFVwVMZjalkZ1X7/beklurlHjE4r78IfeFI2R66upkpiObmu5THCyNkeJPVcGpPDTrpgzcRGtCGAgtTfxRYsIfwdmKutqGfsznxq8k6rzhDbJh6Fy2p89aPBmmeeaN/ul+Kdhr7erNu2cwZm8IBV7HBOSnTUQk/PACqqhzdxL+PgSvjZ6zwlfElb2pfxM6iygxEXb533ZuRQ1EIqG40IViG91GzOZIpR2BcgA0qbQP7oh76bgtfulZTNDpaqv0fB0DQmgleeTFSX0JjzYHeqpUWM0np23ykhksx0jNZGM0wp1pQdhrcMfIqKiLi6cIJ+pcR9GLx6bB8Wjh3WWdJXLsmnW7oAR22CabuzyevozCeFmmKPUd/qjD+Kb8cGI27+1zlt8WyNni6HSwjprcJ69AnhO/Jf0oAurIaPkJcQisVHh4JfNtj0kj5vGeGm4dpGyAPk/NPd0VlOe0LSI1dNCHk5MsVjugzr4IOlvm9r90c4y6r4X8kggQf5k4hQF7afiyxA0vXNQE9V2BC6V6BpCAvhcuZdcDN4DP/XsvRB0Mh1cFdvGasLAUTog8NT1Jm2U/f0UUSOM0GzjsacZtKtQXRdsbUjoyl/QLC7Bw==

4月12日,公司承建的黄骅港三期工程土建、水工及设备三大项全部通过验收,正式交付使用,工程试生产性能稳定。
    工程验收会在黄骅港举行,河北省水运工程质量安全监督局、神华黄骅港务公司、京华监理、中国船级社及公司相关负责人参加了会议。经质检局核定,认为黄骅港三期工程质量合格、工程达标,同意验收。
    黄骅港三期工程是公司首个大型水工总承包项目,合同工期19个月,总造价32.85亿元,于2011年4月20日签订合同并开始施工,经过一年多的不懈努力,公司顺利完成各个节点工期。该工程建设规模巨大,在港口领域首次引进筒仓储煤的环保工艺,翻车机及装船机系统能力均达到国内顶尖水平。该工程正式投产后将为黄骅港煤炭港区新增5000万吨煤炭下水能力。