公司完成港珠澳大桥首件墩台预制

2017-2-28
2013-03-11
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

经过十多天的等待,3月5日,由公司所属五公司负责预制的港珠澳大桥首件墩台成功拆模,正式“亮相”。
    港珠澳大桥首件墩台——31号墩于1月31日开工预制,2月21日浇注完成。该墩台是公司与二公局联合体承建的港珠澳大桥CB03标合同段72座墩台中的一个。CB03标东起西人工岛连接桥,西接深水区CB04合同段,总长8670米。72座混凝土预制墩台中包括非通航孔桥68个桥墩、通航孔桥4个桥墩。墩台为六边形结构,墩身为薄壁空心墩,墩台采用直立式整体或分段预制,单件最大高度26.95米,最大重量3380吨,共需绑扎环氧钢筋约1.7万吨,浇注混凝土8.85万立方米。
    目前,公司正紧张筹备首件评审,并做好其他墩台的施工准备,墩台预制施工即将全面展开。